Rockfall protection at the Dicteon Andron cave of Lasithi (work in progress).

Our company signed a rockfall protection project contract with Lydakis construction  at the Dicteon Andron cave in Lasithi. In this project our goal is to apply 2500 meters of fully compacted anchors with a maximum depth of  8,00 meters and for this project we used 2,000m2 rosette type scaffolding